ENVIRONMENT PROTECTION AND SAFETY
Presidential Decree 1586 of 1978
Requires:
• private corporations,
• firms or
•
entities including agencies and instrumentalities of
the
government
to prepare an Environmental Impact Statement (EIS)
EIS
Environmental Impact Statement
2 factors of EIS System
(1) the nature of the project and its potential to cause
significant
impacts, and
(2) the sensitivity or
vulnerability of environmental resources in
the project area.
EIA
Environmental Impact Assessment
ECC
Environmental Compliance Certificate
ECC is issued by the
by the DENR/EMB after a positive review of an application
Environmental Compliance Certificate (ECC) contains
contains specific measures and conditions that the project proponent has to undertake before and during the operation of a project, and in some cases, during the project's abandonment phase to mitigate identified environmental impacts.
EWP
Environmental Work Program
CEMCRR
Certificate of Environmental Management
and Community Relations Record
Certificate of Environmental Management
and Community Relations Record
proof of satisfactory environmental management and
community
relations in its past mineral resource use or
mining-related ventures
Environmental Work Program
the comprehensive and strategic environmental management plan to achieve the environmental management objectives, criteria and commitments including protection and rehabilitation of the disturbed environment
EPEP
Environmental Protection and Enhancement Program
Environmental Protection and Enhancement
Program
The Contractor shall allocate for its initial environment-related
capital expenditures an amount that shall approximate ten
percent
(10%) of the total capital/project cost or such other amount depending
on the environmental/ geological condition, nature and scale of
operations and technology employed.
AEPEP
Annual Environmental Protection and
Enhancement Program
Contingent Liability and Rehabilitation
Fund (CLRF)
Mine Rehabilitation Fund (MRF)
Mine Waste and Tailings Fees Reserve Fund (MWTF)
Final Mine Rehabilitation/Decommissioning Fund
(FMRDF)
MRF
Mine Rehabilitation Fund
MWTF
Mine Waste and Tailings Fees Reserve Fund
FMRDF
Final Mine Rehabilitation/Decommissioning Fund
Mine Rehabilitation Fund
established and maintained by each operating Contractor/Permit Holder
as a reasonable environmental deposit to ensure availability of funds
for the satisfactory compliance with the commitments and performance
of the
activities stipulated in the EPEP/AEPEP during specific
project phase.
2 Forms for Mine Rehabilitation fund
(1) Monitoring Trust Fund
(2) Rehabilitation Cash Fund
Mine Waste and Tailings Fees Reserve Fund
(MWTF)
Semi-annual
PhP0.05/MT of mine waste produced
• PhP0.10/MT
of mill tailings
FMR/DP
Final Mine Rehabilitation/Decommissioning Plan
or
Mine Closure Plan
Final Mine Rehabilitation/Decommissioning
Plan
integrated in the EPEP and submitted by Contractors/Permit Holders to
the MRF Committee through the Regional Office
and to the CLRF
Steering Committee through the Bureau