front 1 Some advantages to be realized when a ____________ is used to excavate is that it digs straight, vertical side walls (in soil which will stand), it cuts a level floor, and it reduces hand trim to a minimum. | back 1 Power hoe or backhoe |
front 2 If an ASTM standard reinforcing bar has a diameter of 1.00 inch, then it would be classified a ____________ bar. | back 2 #8 |
front 3 A ____________ bond is a bond furnished by the contractor that guarantees they will sign a contract in accordance with their bid and will provide performance and payment bonds. | back 3 Bid |
front 4 If #3 reinforcement bars are to be lapped a minimum of 30 times the bar diameter, the minimum length of bar lap is ____________ inches. Select the closest answer. | back 4 11.25 |
front 5 ____________ is one of the two methods for CPM calculations. | back 5 Arrow diagramming |
front 6 A standard, non-modular brick is ____________ inches long. | back 6 8 |
front 7 Plans and elevations are usually drawn at no less than | back 7 1/8" 1'0" |
front 8 Under the Uniform System developed by the Construction Specifications Institute (CSI) Division 2 includes | back 8 Subsurface Investigation |
front 9 The area of a roof measuring 100'-0" x 100'-0" with a 1⁄4 pitch and a 12" or 1' overhanging cornice is ____________ square feet. Select the closest answer. | back 9 11,632 |
front 10 When excavating sandy clay/moist loam using a hydraulic tractor (crawler) backhoe with a 1-1/4 cubic yard bucket, an average of ____________ cubic yards can be excavated per 8-hour day. Select the closest answer. | back 10 900 |
front 11 The well point method of dewatering is usually | back 11 Used in advance of the excavation |
front 12 ____________ board feet of wood would be required to build a partition wall that measures 8' high x 25' long and is 4" thick with one 2 x 4 sole plate but a double plate at the top. Assume studs are placed 18" on center. Select the closet answer. | back 12 146 |
front 13 If 450 bank cubic yards of dry sand is to be excavated, the number of loose cubic yards that will be excavated is ____________ cubic yards. Select the closet answer. | back 13 495 |
front 14 ____________ is the material or masonry units forming a cap or finish on top of a wall and protects it from penetration of water from above. | back 14 Coping |
front 15 The highest strength mortar is | back 15 Туре М |
front 16 The convenience outlet symbol is defined to be a | back 16 Range |
front 17 A ____________ bond is a bond assuring that the contractor will complete a project in accordance with plans and specs identified in the contract documents. | back 17 Performance |
front 18 An activity with zero float is called a | back 18 Critical activity |
front 19 In estimating quantities of excavation and concrete, both are measured by the cubic yard. One cubic yard contains ____________ cubic feet. | back 19 27 |
front 20 ____________are drawings in which all horizontal and vertical lines have true length and vertical lines are vertical but horizontal lines are set at 30 degrees or -30 degrees. | back 20 Orthographics |
front 21 One mason will lay an average of | back 21 225-250 |
front 22 The ____________method of drilling can only be used for preliminary investigations for foundations. | back 22 Hand auger |
front 23 Most working drawings for building construction are based on | back 23 Orthographic projection |
front 24 Modular face bricks with a nominal brick size of 2 2/3" x 4" x 8" are to be used to face a 2,500 square foot wall without headers. ____________bricks will be required for this job. Select the closest answer. | back 24 16,875 |
front 25 ____________work is usually publicly advertised. | back 25 Public |
front 26 The typical dead weight of a 3/4 inch piece of form plywood is ____________ lbs. | back 26 71 |
front 27 A ____________ contract allows the owner control over the selection of his general contractor. | back 27 Negotiated |
front 28 Once a loan is approved and accepted, ____________is (are) NOT considered a closing cost(s). | back 28 Interest |
front 29 When hauling excavated materials in trucks, the truck capacity should be at least ____________times the dipper or bucket capacity of the excavator. | back 29 Four |
front 30 A contractor can borrow money at 2 points above the current prime rate. This means that | back 30 The interest the contractor will be paying is 2% over the prime rate determines the quality requirements on a project during the process of bidding. |
front 31 ____________determines the quality requirements on a project during the process of bidding. | back 31 Specifications |
front 32 A pneumatic tamper enables a worker to do
nearly | back 32 Ten times |
front 33 ____________is not one of the three traditional methods of construction scheduling. | back 33 Jobsite Project Schedule |
front 34 Most building departments require that plumbing drawings be submitted in a/an | back 34 Isometric riser diagram |
front 35 The maximum distance that can typically be spanned by a wood truss is ____________ feet. | back 35 200 |
front 36 A masonry unit that does not meet standards or specifications and has been rejected is known as | back 36 Culls |
front 37 Any discrepancies on the plans or specifications or changes the architect or owner wish to make after the plans and specifications have been issued, | back 37 Addenda |
front 38 The average life expectancy of truck tires in construction work is ____________hours. | back 38 3,000 |
front 39 The federal government, under the ____________ requires that a contractor furnish two separate bonds, one for performance and one for the payment of labor and materials. | back 39 Miller Act |
front 40 A defect in workmanship is found 18 months after a project is completed. A ____________ bond would cover the repair. | back 40 Maintenance |
front 41 If a contractor regularly operates within an area that requires a permit bond, the cost of this bond should be expensed | back 41 As office overhead |
front 42 An AIA form ____________, the Contractors Qualification Statement, is used to furnish information needed to bid on public work. | back 42 A305 |
front 43 Another reference name for a Bar Chart is a | back 43 Gantt Chart |
front 44 The terms CPM and PERT pertain to | back 44 Scheduling |
front 45 The principal objective of construction scheduling is to manage all of the following resources used in the construction process except for | back 45 Cash flow |
front 46 The standard tool for resource control in project scheduling which calculates the project completion date and dates for completion of project activities and intermediate milestones is the | back 46 Critical Path Method (CPM) |
front 47 2600 L.F. of 2 x 4's is ____________board feet. Select the closest answer. | back 47 1,734 |
front 48 Equipment rental rates vary greatly throughout the country. It is standard practice to base rates on ____________ hours per month. | back 48 176 |
front 49 When renting non-tractor equipment, the ____________is usually responsible for the cost of repairs due to normal wear and tear. | back 49 Leaser |
front 50 The type of excavating equipment selected, as well as the size of the equipment required for a project, should be based on the, | back 50 Volume of material to be moved |
front 51 The average useful life of a 3/4 cubic yard hydraulic backhoe is ____________years. | back 51 7 |
front 52 At a density of approximately 25 pounds per cubic foot, 1" of vermiculite concrete has an insulating value equal to approximately ____________ inches of ordinary concrete. | back 52 16 |
front 53 The R value rating of a masonry wall constructed with 10" thick hollow concrete masonry units with a | back 53 R-7.6 |
front 54 The weight of 150' of 2-1/2" x 2-1/2" x 3/16" steel angles is ____________pounds. Select the closest answer. | back 54 460.5 |
front 55 An 8-inch light weight concrete block has an R value of | back 55 2.00 |
front 56 40,000 pounds will equal ____________metric tons. Select the closest answer. | back 56 18.14 |
front 57 A ____________ arch has horizontal or nearly horizontal upper and lower surfaces. | back 57 Jack |
front 58 Information on the nature or the thickness of underlying subsurface rock is usually obtained by | back 58 Core borings |
front 59 The ____________sheets in the working drawings for a project will include the site survey and grading plans. | back 59 Civil |
front 60 After acquiring a piece of construction equipment, the contractor should | back 60 Develop an hourly rate charge, sufficient to cover interest charges and original investment |
front 61 A blueprint shows a rectangular building lot that scales out a 15.0" by 22.5". The scale given for the site plan is 1" 12". The area of the building lot is ____________square feet. Select the closest answer. | back 61 48,600 |
front 62 ____________is the amount of time that an activity can be delayed and is obtained by subtracting its early start (ES) from its late start (LS). | back 62 Total float |
front 63 Modifications issued after contract is signed are called a(n) | back 63 Change order |
front 64 Well point systems are typically used for dewatering excavations. For specific applications, the general contractor should | back 64 Consult a local dewatering contractor |
front 65 According to a set of plans, a contractor is to construct a residential structure that measures 40' x 60' with a hip slope sloped at 5/12 slope. The total area of the roof is ____________ square feet. Select the closest answer. | back 65 2,600 |
front 66 Architects and Engineers specify that fill material is to be placed in layers from ____________inches and to compact each layer with some sort of roller or tamping equipment. | back 66 6-12 |
front 67 When cutting old or cured concrete, using a diamond blade of correct specification, cutting time may be ____________the amount given for cutting green concrete. | back 67 Double |
front 68 The typical swell factor for an average blasted rock is ____________ %. | back 68 27 |
front 69 Vermiculite is a mineral that expands, when heated, to about ____________ times its original size. | back 69 12 |
front 70 Which of the following statements is NOT correct? | back 70 Total float is obtained by subtracting its' EF from its' ES time |
front 71 Which of the following is NOT an advantage to using Tilt-up wall panel construction? | back 71 Field personnel will be unfamiliar with a new type of construction procedure, rejection and opposition will be encountered |
front 72 A minor arch with a maximum span of 6 feet and a load not exceeding 1000 lb. per foot is typically referred to as a ____________ arch. | back 72 Jack |
front 73 A vertical plane represented by an orthographic projection of the outside building is a (an). | back 73 Elevation |
front 74 ____________standard bricks are required to build an 8" thick 10 ft x 20 ft wall using a 3/8" bed joint. Select the closest answer. | back 74 2,666 |
front 75 If the lap is 4" wide and only a single thickness of felt is used, add about ____________% to allow for laps and the additional felt required at the top and bottom of wall. | back 75 20 |
front 76 A contractor is building a house with a hip roof. The slope of the roof is 5/12. The plan dimensions of the house are 40' x 60'. Assuming a 10% waster factor, the contractor should order ____________ sheets of plywood. Select the closest answer. | back 76 90 |
front 77 A contractor is buying a bundle of 2" x 6" x 8' long. The cost of lumber is $0.25 per BF. If the cost of the bundle is $100, ____________pieces are in the bundle. Select the closest answer | back 77 50 |
front 78 One of the easiest and most frequently used methods of computing grading cuts or fills for a plot plan that shows contours is the ____________ method. | back 78 Cross sectional |
front 79 A contractor has to excavate a drainage swale that is 200' long, 16' wide and has a depth of 2' with the ends vertical. If the soil to be removed is mud, the total volume of material to be removed from the job site would be ____________ cyd. Select the closest answer. | back 79 285 |
front 80 The principal objective of a construction schedule is to | back 80 Efficiently manage resources in order to complete within the estimated time and costs for the project |
front 81 The process of constructing the temporary end of a masonry wall with the end stretcher of every alternate course projecting is known as | back 81 Toothing |
front 82 A shelf or ledge formed by projecting successive course of masonry out from the face of the wall, pier or column is a | back 82 Corbel |
front 83 A method of construction for walls that greatly reduces the investment in large quantities of forming material is known as ____________ construction. In this method, the wall panels are cast on the ground and then raised into position. | back 83 Tilt-up |
front 84 A wall built of the wythes of masonry units, separated by an air space, and tied together is known as a (an). ____________ wall. | back 84 Cavity |
front 85 Another name for a major arch is a ____________ arch. | back 85 Gothic |
front 86 In an ordinary building foundation work, the most common type of pile to be used is | back 86 Cast in place concrete |
front 87 The late start of an activity is the | back 87 Latest it can start without effecting the end date of the project |
front 88 A contractor needs to purchase 25 lengths of structural steel angle, 2 1⁄2 x 2 1⁄2 x 1/2. Each piece of 20' long. The total weight to be purchased is ____________pounds. Select the closest answer. | back 88 3,850 |
front 89 The type of mortar recommended to be used for stone foundation walls is | back 89 Туре М |
front 90 Each of the following factors must be considered when estimating the costs for the excavation of a project. Generally, the easiest to quantify is the | back 90 Volume of material to remove |
front 91 A diesel backhoe has a 175 HP engine. The estimated fuel consumption for the backhoe is between ____________ gallons per hour. Select the closest answer. | back 91 5.95 and 7.00 |
front 92 A contractor is operating a 225 HP backhoe. The machine is operated for 7.5 hours per shift. If the contractor is working 6 days a week and wants to size a fuel tank to give himself a one-week supply of diesel fuel, the tank would need to hold ____________ gallons. Select the closest answer. | back 92 405 |
front 93 A contractor is estimating the amount of roofing material to buy for a project. According to Walker's, a waste factor of ____________% would be used to estimate the quantity of asphalt shingles for a structure with hip roofs, including dormers and valleys. | back 93 20 |
front 94 Based on the house plan below, the total roof area is ____________ square feet Select the closest answer. | back 94 ![]() 4,297 |