front 1 Which of the following is lienable? | back 1 Leased car rental ticket counter in an airport |
front 2 If a "SUMMONS TO SHOW CAUSE" is served upon a lienor, the lien of any lienor upon whom such notice is served and who fails to institute a suit to enforce his or her lien within ________ days, shall have their lien extinguished automatically. | back 2 20 |
front 3 Which of the following is the correct priority of payment for liens claimed under a direct contract? A. Liens of the contractor, liens of all persons other than the contractor, liens of all laborers B. Liens of the contractor, liens of all laborers, liens of all persons other than the contractor C. Liens of all persons other than the contractor, liens of all laborers, liens of the contractor D. Liens of all laborers, liens of all persons other than the contractor, liens of the contractor | back 3 D. Liens of all laborers, liens of all persons other than the contractor, liens of the contractor |
front 4 Which of the following have lien rights? 1. Laborer | back 4 1, 2, and 3 |
front 5 One way an owner can minimize the risk of having a lien filed on his or her property is to | back 5 Have the contractor obtain a payment bond |
front 6 A claim of lien may be recorded at any time during the progress of the work or thereafter but not later than________ days after the final furnishing of the labor, services, or materials by the lienor. | back 6 90 |
front 7 The only method of extending a Claim of lien beyond the one-year deadline is if | back 7 An action is filed in court to enforce the lien |
front 8 Notice to Owner must be served by a subcontractor before commencing, or not later than______days after commencing furnishing services or materials. | back 8 45 |
front 9 A lienor, who is a privity lienor and does not need to serve a Notice to Owner is one | back 9 With direct contract with the owner |
front 10 A contractor must serve a copy of the claim of lien on the owner and lender (if any) within how many days of the date the claim of lien is recorded? | back 10 15 |
front 11 If the direct contract is greater than_________, the applicant shall
file with the issuing authority prior | back 11 $2,500 |
front 12 The contractor's final payment must be delivered to the owner no later than _________ days before suit is filed to enforce the contractor's lien, even if the final payment has not yet become due. | back 12 5 |
front 13 The Lien Laws require that any person who receives funds for
constructing or altering improvement, use the funds to pay others for
services and materials provided in connection with the project. | back 13 Criminally prosecuted under the Lien Law for felony and subjected to discipline under the Contractor Licensing Law |
front 14 is one of the generally two types of releases. | back 14 Release through time certain |
front 15 According to Florida Construction Lien Laws, which of the following is considered an improper payment by an owner to a contractor? | back 15 Payments made by owner after a Notice to Owner has been served and before a waiver has been obtained by the owner |
front 16 When may a person who has delivered materials that were unused for an improvement peaceably repossess and remove such materials? | back 16
|
front 17 How long does a clam of lien last? | back 17 1 year |
front 18 What is required to file a construction claim of lien? | back 18 The claim must be recorded with the clerk of the court in the county where the improved property is located |
front 19 An owner may terminate Notice of Commencement by executing a Notice of Termination that contains the following except | back 19 Two copies of a Notice Direct Contract |
front 20 If an owner makes payment to a contractor, without requiring a final payment affidavit (a/k/a contractor's affidavit), the payments are considered_______payments. | back 20 Improper |
front 21 Even though lien rights exist against a property owned by one or both married persons, and the contract is only signed by one of the two and the married couple is not separated and living apart, the non-signing spouse can object within ________ days of learning of the contract and there will be no lien rights. | back 21 Ten |
front 22 All of the following are part of the amount necessary to transfer a lien to a bond or cash except | back 22 $25 filing fee |
front 23 A Notice of Lien filing or a Notice to Owner shall be given to the Owner via | back 23
|
front 24 A recorded Notice of Commencement will expire in 90 days unless | back 24 Work has commenced |
front 25 If an owner fails to file a Notice of Commencement on a project with a total cost of $10,000, the contractor will initially be unable to obtain | back 25 Approval of Building Inspections |