front 1 The foundation footers marked with the grid point C5 will require
____________ cubic yards to pour. | back 1 28 |
front 2 __________inches of compacted limerock are to be placed beneath the asphalt surface of all parking areas. | back 2 6 |
front 3 ___________measured in-place cubic yards of topsoil are required for
the planters if the topsoil layer is 10 | back 3 2.00 |
front 4 This project will require ___________ lineal feet of fencing to
enclose the property. There are three (3) 8 ft | back 4 1,462 |
front 5 The distance from point C to point D is ___________ yds. | back 5 175 |
front 6 A fencing contractor is invited to submit a bid to enclose the entire
site in 6' construction site security | back 6 $14,000 |
front 7 The Job Status Report, which indicates the percentage completed by
each major construction activity, is | back 7 Project Engineer or Field Superintendent |
front 8 A demolition first inspection shall be made ___________________ . | back 8 After all utility connections have been disconnected |
front 9 A contractor wins a job for a low bid of $120,000. If his total costs
and expenses are $90,000, his margin of | back 9 25 |
front 10 A proposal is a legal instrument that will NOT bind the Contractor to the Owner if _____________. | back 10 The contractor forfeits the bid bond. |
front 11 Submittal documents shall be submitted in ___________ or more sets with each permit application. | back 11 2 |
front 12 A business’s__________ insurance shall apply if property damages
caused by construction are | back 12 General Liability |
front 13 Nightclubs and restaurants are classified as Group ___________________ occupancies. | back 13 A-2 |
front 14 A (The)___________ is (are) NOT required for a minimum plan review
prior to building permitting by | back 14 Plumbing elevations |
front 15 ____________ is (are) NOT required to be stored at the construction site by the Contractor. | back 15 Material invoices |
front 16 A general, building, or residential contractor is NOT required to
subcontract the installation of wood | back 16 On new buildings of their own construction |
front 17 A Notice of Commencement has not been filed on a $10,000 project. The
initial indication of a problem | back 17 The first building inspection |
front 18 __________________ is a non-operable fenestration unit primarily
designed to transmit daylight from a | back 18 Tubular Daylighting Device (TDD) |
front 19 The vertical clearance from the public right-of-way to the lowest
part of any awning shall be not less than | back 19 7 |
front 20 One set of approved construction documents shall be retained by the
building official for a period of not | back 20 180 |
front 21 If there are multiple liens on a project, only a limited amount of
funds to pay the liens, and all liens were | back 21 Liens of laborers |
front 22 The _____________ is authorized to issue a stop work order. | back 22 Building official |
front 23 _______________ the company is in charge of the safety program. | back 23 One person within |
front 24 Installing a/an ____________ does NOT require a permit. | back 24 portable cooling unit |
front 25 A permit from the ________________________ is required prior to the
start of construction of a habitable | back 25 Florida Department of Environmental Protection |
front 26 ________________ is true regarding Surety Bonding. | back 26 Losses are not contemplated |
front 27 When developing a schedule using a Project Logic Table, _________should NOT be considered. | back 27 Crew size and Manpower Levels |
front 28 A general “rule of thumb” for calculating the bonding capacity of a
contractor is to determine the net | back 28 10 |
front 29 _______________ would result in disciplinary action by the licensing board. | back 29 Intimidating, threatening, coercing, or otherwise discouraging the
service of a notice to owner or a |
front 30 Prior to the settlement of an insured loss, the Owner shall notify
the Contractor of terms and the | back 30 14 |
front 31 If a contractor paid $3,875 for supplies which included 7% sales tax,
the cost of the supplies without the | back 31 $3,622 |
front 32 CSI MasterFormat divides specifications into ________ specific divisions. | back 32 50 |
front 33 Regarding certification of registered contractors, which of the
following is NOT a requirement a | back 33 Has at least 6 years of active, probation experience in that contracting category |
front 34 If the Contractor encounters concealed physical conditions that
differ material from those indicated in the | back 34 14 days after first observance by Contractor |
front 35 The difference between the cash received and the principal due at the
end of a discount loan is known as | back 35 Discount |
front 36 A building demolition specialty contractor is a contractor who has
the skill to demolish structures | back 36 50 |
front 37 ______________________ need (s) to have a license in the State of
Florida to do construction/contracting | back 37 A handyman who has a $1,500 project |
front 38 A person who willfully files a fraudulent lien is guilty of a ___________. | back 38 Third degree felony |
front 39 Failure to furnish a sworn statement within _____________ days shall result in the loss of lien rights. | back 39 30 |
front 40 The contractor must, within _______________ days after receipt of the
owner’s written request, furnish to | back 40 10 |
front 41 The Architect will prepare a Construction Change Directive __________________. | back 41 In the absence of total agreement on the terms of a Change Order |
front 42 Long lead items should be _____. | back 42 Identified and ordered early |
front 43 EPA asbestos regulations for demolition of commercial, industrial,
and publicly owned buildings and | back 43 At least 10 working days before beginning the demolition |
front 44 The Construction Change Directive when prepared does not have to be signed by the ____________. | back 44 Contractor |
front 45 The log and summary, OSHA No. 300/300A, should be kept for ______
calendar years following the end | back 45 5 |
front 46 If the Initial Decision Maker requests a party to provide a response
to a Claim or to furnish additional | back 46 10 |
front 47 The Florida Civil Rights Act of 1992 (FCRA) does NOT prohibit
employment discrimination based | back 47 Drug Abuse |
front 48 An Installation Floater is an insurance policy that covers ______. | back 48 Subcontractor materials in transit |
front 49 __________ is the minimum fine to be cited by OSHA for a willful serious penalty. | back 49
|
front 50 A contractor is hired to paint a stucco wall. The wall is 3000 ft
long by 10 ft high and contains 20 | back 50 $7,400 to $7,449 |
front 51 The total Labor and Materials cost for a project was estimated to be
$266,000 and 55% was estimated for | back 51 $17,955 |
front 52 In a precedence diagram, lines linking the boxes are called ________________ . | back 52 Connectors |
front 53 Fictitious names are valid for ______ years. | back 53 5 |
front 54 ________________ are employers that are NOT exempt from the broad coverage of OSHA. | back 54 Airport convenience stores |
front 55 The ______ ACT protects covered employees against retaliation for
participation in an investigation, | back 55 Public Whistle-blowers |
front 56 A secondary qualifying agent is responsible for ________. | back 56
|
front 57 A contract was signed by all parties on July 1, 2018. The date of
commencement was given as July 9, | back 57 July 27, 2018 |
front 58 ______________________in any action against an unlicensed contractor
for injuries sustained resulting | back 58 The consumer is entitled to three times the actual damages sustained, plus costs and attorney's fees. |
front 59 The _________________ shall not permit any part of the construction
or site to be loaded so as to cause | back 59 Contractor |
front 60 If you pay an independent contractor at least $600, it is your responsibility to _______________. | back 60 File a 1099 |
front 61 Movable fabric awnings or fabric covered frames may extend over
public property for a distance of not | back 61 5 |
front 62 ___________________ does NOT need to be written to be enforceable. | back 62 An agreement for the sale of goods less than $500 |
front 63 ____________ for latent defects discovered on a project. | back 63 The contractor's liability is subject to the statute of limitations. |
front 64 A project requires 388,000 lbs. of steel beams and columns. Delivery
charges this year are 7% greater than | back 64 $885.00 |
front 65 The _______________ shall directly arrange and pay for tests,
inspections, or approvals where building | back 65 Owner |