Print Options

Card layout:

← Back to notecard set|Easy Notecards home page

Instructions for Side by Side Printing
  1. Print the notecards
  2. Fold each page in half along the solid vertical line
  3. Cut out the notecards by cutting along each horizontal dotted line
  4. Optional: Glue, tape or staple the ends of each notecard together
  1. Verify Front of pages is selected for Viewing and print the front of the notecards
  2. Select Back of pages for Viewing and print the back of the notecards
    NOTE: Since the back of the pages are printed in reverse order (last page is printed first), keep the pages in the same order as they were after Step 1. Also, be sure to feed the pages in the same direction as you did in Step 1.
  3. Cut out the notecards by cutting along each horizontal and vertical dotted line
Print these notecards...Print as a list

12 notecards = 3 pages (4 cards per page)

Viewing:

Quiz 5

front 1

An output of the determine budget process is the cost baseline. How is this baseline commonly displayed?

a) S-curve
b) Gantt chart
c) Pie chart
d) Bar chart

back 1

a) S-curve

front 2

Analogous cost estimating:

a) Integrates bottom-up estimating techniques with relevant statistical relationships to estimate the cost of the current project
b) Summarizes estimates for individual work packages to estimate the cost of the current project
c) Is used most frequently in the later phases of a project
d) Relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project

back 2

d) Relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project

front 3

Consider the following cumulative measure: BAC = 200, AC = 120, EV = 80, CPI = .666. Predicting that all future work will be accomplished at the budgeted rate, the estimate of what the project will cost when it is completed is:

a) 240
b) 120
c) 160
d) 200

back 3

a) 240

front 4

Consider the following cumulative measures: BAC = 200, AC = 120, EV = 80, CPI = .666. Predicting that what the project has experienced to date can be expected to continue in the future, the estimate of what the project will cost when it is completed is:

a) 220
b) 300
c) 320
d) 240

back 4

b) 300

front 5

Control costs includes all of the following EXCEPT:

a) Monitoring cost performance to isolate and understand variances from the approved cost baseline
b) Allocating the overall estimates to individual work packages to establish a cost baseline
c) Monitoring work performance against funds expended
d) Informing appropriate stakeholders of all approved changes and associated costs

back 5

b) Allocating the overall estimates to individual work packages to establish a cost baseline

front 6

If your earned value is equal to your actual cost, it means:

a) Cost variance is 1
b) Work so far is costing what you expected it to cost
c) Project is on budget and on schedule
d) Schedule variance index is 1

back 6

b) Work so far is costing what you expected it to cost

front 7

The focus of reserve analysis when estimating costs is ________ , whereas the focus of reserve analysis in determining budget is _______ .

a) Monetary reserves; management reserves
b) Contingency reserves; management reserves
c) Management reserves; contingency reserves
d) Contingency reserves; schedule reserves

back 7

b) Contingency reserves; management reserves

front 8

Which of the following statements regarding To-Complete Performance Index (TCPI) is true?

a) TCPI is a forecasting metric
b) TCPI is a ratio of remaining funds to remaining work
c) TCPI is a tool and technique used in performing the Determine budget process
d) A project with a TCPI value of .80 is a cause for concern

back 8

a) TCPI is a forecasting metric

front 9

You are a project manager currently working with a defense contractor that is experiencing unusual cost overruns because of a recent unpredicted spike in the price of crude oil. Most economists predict this high energy cost to be temporary. You also know EV = 125, CPI = .625, ETC = 475, BAC =600, PV = 250, and AC = 200. Based on this information, what is EAC?

a) 960
b) 500
c) 675
d) 100

back 9

c) 675

front 10

You are concerned that your project will be over budget when it is finally completed. In order to confirm or allay your fears, you use the following information to make some calculations: AC = 305, PV = 285, EV = 325, ETC = 200, and BAC = 400. Based on these figures, what do you know?

a) CPI is .94. Costs appear to be under control.
b) CPI is 1.07. Costs appear to be under control.
c) CPI is negative. You should be worried.
d) CPI is positive but less than 1.0. You should be worried.

back 10

b) CPI is 1.07. Costs appear to be under control.

front 11

The total project budget is $1,000. 80% of the total work should be completed as of today. Today, you see that 60% of the total work is complete. You have spent 50% of the project budget. At this point, your SPI is:

a) 1.20
b) .75
c) .83
d) 1.33

back 11

b) .75

front 12

You used 3-point estimating to arrive at an expected duration of 110, and you know the standard deviation of that distribution is 12. Which of the following is true?

a) There is approximately a 75% change of completing this activity in 86 to 134 days.
b) There is approximately a 95% chance of completing this activity in 98 to 122 days.
c) There is approximately a 99% chance of completing this activity in 86 to 134 days.
d) There is approximately a 68% chance of completing this activity in 98 to 122 days.

back 12

d) There is approximately a 68% chance of completing this activity in 98 to 122 days.