The filter lens shade number to be used when light cutting up to 1 inch shall be ____________.
3 or 4
If an infringement of a copyright or patent is discovered by, or made
known to, the Contractor, the
_______________shall be responsible
for the loss unless the information is promptly furnished to the
Architect.
Contractor
A contractor is performing an estimate on a building with drawings
scaled to 3/8" = 1' 0". The contractor then
measures 4
(7/8)" on the drawings as ____________________
13' 0"
The contractor’s final payment affidavit must be delivered to the
owner no later than ____________ days
before suit is filed to
enforce the contractor’s lien, even if the final payment has not yet
become due.
5
Those liens to be paid last are the _______________.
Liens of the contractor
It is important that slab formwork measuring 42’-0” x 74’-0” be
square before concrete is poured. The
diagonal measurement to
ensure the formwork would be square is______________. Select the closest
answer.
85’ -1”
The thickness of blown-in insulation shall be written in inches on
markers that are installed at least one for
every ________ square
feet throughout the attic space.
300
Where equipment replacements and repairs must be performed in an
emergency situation, the permit
application shall be ___________ .
Submitted the next working business day after the replacement/repair has been completed
A secondary qualifying agent has pulled a permit for a building
project. There is a problem with payment to
a subcontractor, the
_____________is (are) responsible for the payment to the subcontractor.
Primary qualifying agent
The Workers’ Compensation Law Act requires the employers carry
insurance to cover employee’s
economic losses resulting from
on-the-job injuries, regardless of fault, and the penalty for not
carrying this
insurance is a fine of not more than _____________
and a possible criminal conviction.
$500
Asbestos can only be removed by a ______________________.
Licensed Asbestos Contractor
The Subcontractor shall make all Claims promptly to the Contractor
for additional cost, extensions of time
and damages for delays
and such claims shall be received by the Contractor not less than
___________
days preceding the time by which the Contractor’s
Claim under the Prime Contract must be made.
Two working days
If a contractor receives a deposit of $20,000 on a contract requiring
a building permit with a total contract
value of $150,000, he
must apply for the applicable building permit within _________ days.
30
A claim of lien is effective for ___________ from the date on which it is recorded.
1 year
The Owner shall furnish to the Contractor, within __________ days
after receipt of written request,
information necessary for the
Contractor to evaluate, give notice of, or enforce mechanic’s lien rights.
15
Orders imposing disciplinary action for local disciplinary action
against a contractor shall contain all of the
following except ___________________.
An invoice for all fines and penalties
Addenda will be issued no later than _________ days prior to the date for receipt of Bids.
4
The owner may terminate the period of effectiveness of a notice of
commencement by recording a notice of
termination that contains a
statement of the date as of which the notice of commencement is
terminated,
which date may not be earlier than _________ days
after the notice of termination is recorded.
30
A _____________ provides a monthly indication of the contract value,
cost expenses to date as well as a
projection of costs to
complete each item of work.
Monthly indicated outcome report
The contractor shall promptly provide notice to the owner and
architect before conditions are disturbed and
in no event later
than _________ days after first observance of the conditions.
14
Billings for work performed or costs incurred by one party that, in
accordance with the agreement, should
have been performed or
incurred by the party to whom billed is called ________________.
Back charges
The project construction schedule should be updated at least once every ___________ days.
30
The number of squares of roofing materials to be ordered for a roof
with dimensions 68’ x 62’ 6” and a
pitch of 5/12 is
_________________. Select the closest answer.
55.50
Prior to the settlement of an insured loss, Owner shall notify
Contractor the terms of the proposed
settlement and the
Contractor shall have ___________ days from receipt of notice to
object to the proposed
settlement or allocation of the proceeds.
14
The ___________________ owns the float.
First to use
The Contractor has achieved substantial completion on a $1,380,200
contract. Previously payments made
total $987,300 and a 10%
retainage was being held. The current payment due is ______________.
$254,880
The maximum fine to be imposed for obtaining a license through fraud or misrepresentation is _______.
$10,000
The issuance of a Certificate for Payment will constitute a
representation by the ____________ that the
work has progressed
to the point indicated and the quality of work is in accordance with
the Contract
Documents.
Architect
The slope of a parking lot that drops 8” in 90 is _______________.
.0074
The Notice of Commencement shall be the responsibility of
____________________to be recorded in the
Clerk’s office prior to
commencing work.
The Owner
A permit issued shall be come invalid if the work authorized by such
permit is suspended or abandoned for
a period of __________ after
the time the work is commenced.
6 months
The grade of a parking lot that drops 8” in 90 is _______________%.
.74
Under the completed contract method, the contractor may recognize the profit ______________.
When the project is nearly complete
If there is a 47 ft long 2 x 4 x 8 ft partition wall with the studs
spaced 16” on center and it has a double top
plate and a single
base plate, ___________________bd ft will be ordered to build this wall.
291.33
The subcontractor shall correct, repair or replace defective work
within __________ hours after receiving
notice of defective work
from contractor.
24
A HP 14 x 89 weighs _______________ lbs. per square foot.
89
The _________________________ method for recording income is the most
preferred method for
accounting statement presentation.
Percentage of completion
For a labor (manpower) estimate, there are various factors which
affect production and would include all of
the following except_____________,
Supervision available on site
A room or space used for assembly purposes less than 750 square feet
in area and accessory to another
occupancy shall be classified as
an __________ occupancy.
Group B
_____________ means that goods first added to inventory are assumed
to be the first goods sold from
inventory.
FIFO
A good preliminary labor estimate should vary less than ____________ percent.
15
The CSI MasterFormat classification system has __________ technical divisions.
49
Claims by either the Owner or Contractor shall be initiated within
________ days after occurrence of the
event giving rise to such
claim or within ____________ days after the claimant first recognizes
the
condition, whichever is later.
21
The business organization must notify DBPR of the termination of the
qualifying agent and obtain another
qualifying agent with
____________ days.
60
The Contractor shall pay the Subcontractor each progress payment no
later than ___________ working days
after the Contractor receives
payment from the Owner.
7
After relocating his business to a new location, the Contractor has
________ days to notify the Board office
of his new address.
30
An order for a minor change in the Work may be issued by the _______________ alone.
Architect
Laborers that are average trained, have fair morale and a normal
absence rate would have a production
efficiency rate of
_____________ percent.
55 to 85
If a restaurant has an approved occupancy for 1,000 people, the
minimum number of required accessible
parking spaces shall be ____________.
20
The Architect will have control over or charge of all the following except for ______________.
Subcontractors
In the event of the death of the qualifying agent, _____________ may
finish an existing project that is under
contract with the
deceased qualifier.
Any one
Elevators shall be provided with Phase I emergency recall operation
and Phase II emergency in-car
operation in accordance with _______________.
ASME A17.1
_______________ insurance covers subcontractor materials on job
sites, while in transit or while stored at
temporary locations.
Installation floater
________________ is NOT an advantage of Network Analysis
Determining the longest length of time that the project can be completed
The Owner may ____________ terminate the Contract for the Owner’s convenience and without cause.
At any time
Any person who commences any work before obtaining the necessary
permits shall be subject to
____________.
A fee established in addition to the required permit fees
__________________ is a procedure under which progress billings are
accelerated in relation to costs
incurred.
Front end loading
Once the subcontractor is officially terminated, the contractor should ______________________.
Leave all the subcontractor’s equipment and materials on site until
subcontractor’s work is
completed
One of the three C’s of underwriting Bonds is NOT ____________.
Contract
______________________ shall be used in the absence of total agreement on the terms of a Change Order.
A construction change directive
The original contract amount is $252,134.00. The sum of the previous
change orders was $12,125.00 and a
third change has a value of
$2,134.00 which includes a profit of $213.00. The new contract value
would be
_________.
$266,393.00
The Bidder shall deliver the required bonds to the Owner not later
than ________ hours following the
execution of the Contract.
72
The required amount of property damage insurance coverage a general
contractor will obtain and maintain
is ______________.
$50,000
The Architect may order minor changes in the Work that are consistent
with the intent of the Contract
Documents and _____________.
Shall be in writing
_________________ contracts normally contain a ceiling price.
Cost plus