Contract Administration Practice Exam #1 Flashcards


Set Details Share
created 2 months ago by TKNotecards
3 views
updated 2 months ago by TKNotecards
show moreless
Page to share:
Embed this setcancel
COPY
code changes based on your size selection
Size:
X
Show:

1

On sheet 2 of 15 of plan set #9501, the distance from gridline point D1 to gridline point D12 is _________ ft.

134

2
card image

187

3

__________cubic yards of concrete are required to pour all the foundation footings marked as #5 locations. Do not deduct for the volume of any steel reinforcing. Select the closest answer.

20

4

___________18H5 bar joists are required for the project's main tower roof framing.

54

5
card image

The distance from point B to point C on the plan is _________ ft.

301.04

6
card image

The Owner wants to install sod on his property. The contractor will order _____________ square foot of sod for his property. Select the closest answer.

65,000

7

The total Labor and Material cost for a project was estimated to be $250,000 and 55% of that total was estimated for Materials. The additional profit on the job will be ____________if actual Labor costs were only 85% of the estimated Labor costs.

$16,875

8

Temporary structures shall have an exit access travel distance of ______ feet or less.

100

9

Ownership passes to the company at the point where the goods are FOB or ____________.

Free on board

10

In the state of Florida, _____________requires a license.

A contractor repairing damaged storm shutters for $1500.

11

The first offense by a person falsely presenting themselves as a licensed contractor is a ________.

First degree misdemeanor

12

In a threshold building, the contractor's contractual or statutory obligations shall not be relieved _____.

By any action of the special inspector

13

The burden of proof of the merit of any proposed substitution is upon the _________.

Proposer

14

A(an) _______________warranty work in construction would be used for its intended purpose.

Implied

15

If the Subcontractor fails within _______ days after receipt of written notice from the Contractor to correct defective Work, the Contractor may make good such deficiencies.

Five working

16

The Architect will _________ after receipt of a Contractor's Application for Payment, either issue to the Owner a Certificate for Payment or notify the Contractor and Owner in writing of the Architect's reasons for withholding certification.

Within seven days

17

According to the Davis-Bacon Act, the ______ may withhold contract payments to cover alleged under-payments of wages.

Secretary of Labor

18

If you are not in direct privity of contract with the owner, the Construction Lien Law requires that you _______________.

Serve a notice to owner

19

If a #2 framing lumber is selling for $6.50 per board-foot, the cost of 820 lineal feet of 2x4, 686 lineal feet of 2x6 and 243 lineal feet of 2x8 would be ________________. Select the closest answer.

$10,120

20

Building inspections shall include ___________________.

Foundation, Framing, Sheathing, Roofing and Final inspections

21

Temporary sanitary facilities and drinking water are typically covered by the ________ of a contract.

Supplementary General Conditions

22

________________ limit is NOT one the limits of liability under a Commercial General Liability insurance policy.

Property damage during construction

23

A Contractor submitted an application for a progress payment. The project has a $246,000 contract amount and was 66% complete at the time of the payment application. The Architect did not certify $22,000 of the requested amount. The retainage rate is 10%. The Contractor should expect to receive _____________.
Select the closest answer.

$126,325

24

Change Orders with back charges to the Contractor when the Owner corrects defective work shall include _____ costs of correcting such deficiencies.

Reasonable

25

A permanent sign identifying the termite treatment provider and need for reinspection and treatment contract renewal shall be provided and posted near the _______.

Water heater or electrical panel

26

Because inventory is consumed over a relatively short period of time, usually not exceeding one year, it is regarded as a __________ of a company.

Current asset

27

____________is an example of work that does NOT require a building permit.

Installing portable ventilation equipment

28

Addenda are modifications to or interpretations of the Bidding Documents and will be issued ______.

No later than four days prior to the date for receipt of Bids

29

Construction materials and equipment shall not be placed or stored within ___________ feet of a street intersection.

20

30

In general, a contract ________ should be recognized as complete under the completed contract method.

In excess of 98% or 99% completed

31

All employers with _______ employee(s) must maintain an OSHA 300/300A log.

Eleven

32

In network construction, _______________are those which are based upon physical characteristics of the work and is normally inflexible.

Hard dependencies

33

It is estimated that the Contractor will need to purchase 250 2 x 4’s that are only available in 10 ft lengths.
If the lumber yard pricing per board foot is $6.50 and sales tax is 7%, the amount to be budgeted should be ___________________. Select the closest answer.

$11,600

34

Among the State requirements for educational facilities is the requirement that new buildings, additions, renovations and remodeling shall not be occupied until the building has received a (n) _______.

Certificate of occupancy

35

The Contractor shall NOT be responsible for __________________.

Scheduling safety compliance inspections

36

__________________________ are NOT items that are included in the general conditions of a contract.

Jobsite offices

37

A Subcontractor may terminate a Subcontract for nonpayment of amounts due for______ days or longer.

60

38

Alterations made to provide an accessible path of travel to the altered area will be deemed disproportionate to the overall alteration when the cost exceeds ______________ percent.

20

39

An accurate estimating method that lists all materials and labor needed for an element of work or project is called _________________ method.

Detailed survey or piece

40

Under the legal principal of _____________, a contractor may be entitled to a reasonable value of the work requested and performed even without reaching an agreement.

Quantum meriut

41

Under FL Lien Law, a person who knowingly uses funds paid on account of a $950 project without paying subs, suppliers and/or laborers is guilty of misapplication of construction funds has committed a _________.

Felony of the third degree

42

Walkways for pedestrians in front of demolition projects during the renovation of an existing building shall be of sufficient width to accommodate pedestrian traffic but in no case shall ______.

Not be less than 4 feet in width

43

The ___________________ method is the simplest method of accounting control of inventory.

Average cost

44

A __________________ clause is typically found in subcontract agreements between the contractor and
subcontractor.

Flow down

45

The date for receipt of bids for a project is Friday, Oct 9. The last date on which Addenda modifying the bid documents may be issued is _______________.

Thirty

46

The date for receipt of bids for a project is Friday, Oct 9. The last date on which Addenda modifying the bid documents may be issued is _______________.

Sunday, Oct 4

47

The fee owner of a threshold building shall select and pay all the costs of employing a special inspector, but the special inspector shall be responsible to _______.

The enforcement agency

48

The ___________owns the drawings for a completed project.

The Architect

49

A concrete slab 140'-8" long, 75'-10" wide and 9-1 /2" thick will require __________cubic yards of concrete. Select the closest answer.

Between 300 and 325

50

An application for a permit for any proposed work shall be deemed to have been abandoned ___________ days after date of filing.

180

51

A ___________________ bond exempts the owner’s real property from claims of lien.

Payment

52

The Subcontractor shall furnish the Contractor periodic progress reports ________ on the Work of this
Subcontract.

As mutually agreed

53

In cases of Claims for additional time due to a continuing delay, ______.

Only one Claim is necessary to be filed

54

Construction lien law is NOT applicable to ______.

Public property

55

General Contractor license holders are NOT required to subcontract _______________.

The installation of wood shingles, wood shakes, or asphalt or fiberglass shingle roofing on new buildings of their own construction

56

The construction manager contracts and acts as agent for the owner in a ______________ contract.

Construction management contract

57

The maximum fine to be imposed on a contractor for working with a delinquent license and it is a second
offense would be __________________

5,000

58

Trusses on a new, single-family detached residential project, shall be inspected ______.

By the building official during the framing inspection

59

Allowances do NOT include ______________________.

Applicable trade discounts

60

Any required certificates of inspection shall be secured by the ______.

Contractor

61

The cost to backfill and compact a 15 ft x 25 ft x 5 ft deep excavation with vertical sides if the excavation contractor charges $1.75 per square foot for each 6-inch lift is________________. Select the closest answer.

$6,565

62

An approved water supply for fire protection shall be made available _______.

As soon as combustible material arrives on the site

63

Requests for clarification or interpretation of the Bidding Documents shall reach the Architect at least
_______ days prior to the date for receipt of Bids.

Seven

64

An employee who feels they have been discriminated against because they reported a suspected OSHA violation may file a complaint with the nearest OSHA office within ______ days of this alleged discrimination.

30

65

In the contract provisions, insurance to be maintained by contractor will be specified in the ____________.

Proposal